Why Do Owners, Designers, Architects & General Contractors use DIRTT Prefab Solutions?
Because its faster, cleaner, safer and more sustainable and there are no change orders.
In the following video you will hear why Withum and their architects used DIRTT prefab in their project.
Following below the video, see specifics of how DIRTT is faster, cleaner, safer and more sustainable than conventional construction.
Withum, a top national accounting firm used DIRTT. When the architect put the plan together, he blanked out the plan so the GC could have a really good understanding of the efficiencies by installing everything about the ceiling in one shot with no walls to work around.
There were ladders everywhere, yet all the trades were allowed efficient easy access to the entire area. No one was held up waiting to get past someone up on a ladder in a hallway. And there was no more moving construction materials from inside one room, down the hall and into another room as there were no interio steel stud walls to maneuver through.
There were zero change orders on the DIRTT prefab portion of the project and the DIRTT project came in at $32 per square foot as planned.
What changes when using Prefab Construction?
Both conventional construction and prefab construction start
with the same empty space after demo is done. Mechanical heating & cooling ducts, along with sprinkler lines being installed below the deck.
Conventional sites
Steel studs get installed early on so
electrical and data work can be run within
the walls, restricting sub-trade movement
to corridors and doorways
Prefab Construction Site
Remains wide open allowing electrical
and data work to be done safely
and more efficiently
and the site remains a lot less congested
Conventional Site
continues to become more congested with drywall & insulation.
Site becomes difficult to navigate as
trades need to work on ladders taking up the entire hallway.
Prefab Construction Site
Remains wide open allowing ceiling grid, lights,
electrical and flooring to be installed quicker and safer.
====
Prefab site progression photos below
Conventional Construction project schedule on the left has work completed in week 17 but using DIRTT prefab construction has the same project completed in week 13.